Gas-based CCHP
Our Business / Gas-based CCHP

Gas-based CCHP

We have participated in the largest gas-based CCHP project in the five northwestern provinces.

  • The largest and most advanced GIS (Gas Insulated Switchgear): ensure stable operation of the grid
  • Installation of gas turbine SGT5-2000E: operating temperature reaches 1500 ℃
  • Installation of steam turbines & waste heat recovery boilers
  • Cooling tower construction with height of 20m
  • Construction of main powerhouse with 243m wide-range grid structure: ensure structural stability
  • Total installed capacity hits 1200 MW, including 5x 230 MW units & 1x 64 MW unit
  • 220 kV power line with distance of 30KM

Hangjinqi to Yinchuan Long Distance Natural Gas Pipeline Project Enters to Final Strech